On Tuesday, Sept. 20 crews will start working on Dean Road. The work will start with grading from Wednesday, Sept. 21 to Friday, Sept. 23 followed by paving on Monday, Sept. 26 and Tuesday Sept. 27.
Crews will be removing the curb off Bonnie Drive and Galloping Hill on Wednesday, Sept. 21 and Thursday, Sept. 22 and reclaim Galloping Hill on Friday, Sept. 23 before grading on Friday Sept. 23 and Monday, Sept. 26. Finally they will pave Galloping Hill on Wednesday, Sept. 28.
They will reclaim, mill and grade Bonnie Drive on Wednesday Sept. 28 and Thursday Sept. 29 followed by paving Bonnie Drive on Sept. 30